Hi

i have a problem with inspectn plan

material have an 2 inspetion plans (group no are differtent 1001 and 1002)

both are valid upto 31.12.9999

when am i post the GR for material goes to quality inspection mode..inspection lot has generated but there task list spection has not captured.. then i go to change inspection lot and assign manually...(1001 or 1002)..then do result regarding and UD

now i used insp plan 1002 .... how i configure to system ...system taken it self by default...1002 always how..

regards

ses

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Its SAP default when you have two or more task list with same validity date & no vendor maintained in the "material assignment" in the task list header....no task list will automatically attached after lot creation...

now

1.Either put deletion flag to one task list.

2.use the user exit QPAP0002 Enhancement for material/plan assignment, plan selection