on 11-15-2010 9:53 PM
Hi All,
I have a situation where we are feeding SNP planned orders using /sapapo/lcin (Time series to Order Network). When we use this transaction SNP planned orders are created in SNP but PDS is not attached to such orders. I would like to know how can I get PDSs attached to SNP planned orders created?
Regards,
Harshil Desai
Hi,
1. Check for the validity of the PDS and Lot size details.
2. Check in the Planning version whether SNP No Planned Order indicator is set.
Thanks,
nandha.