Exempt labour cost in IMG but still include in the Budget Availability Chec

0 Kudos

Dear expert,

I am confusing in setting which is under SPRO->Project Systems->Cost->Budget->Specify Exempt Cost Elements. I have set the labour cost element in the table, but when I do a budget availability check, it will include the labour cost.

Does anyone know how to make this setting working?

Thanks in advance.

regards,

FLL

Accepted Solutions (1)

Accepted Solutions (1)

raghavendra_praveen
Active Contributor
0 Kudos

Hi

When you include the cost element (with controlling area) in OPTK transaction then any costs on that particular cost element will not be considered in availability check if your network/WBS element belongs to same controlling area. Even though its value is counted but when you check up assigned value this cost element cost will be exempted, You can check that in CJ30 transaction -> extras -> availability information.

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

Can you tell me how did you do the budget availability check? This will help us to simulate your scenario in our system and see where the problem is.

0 Kudos

Hi,

Thanks to Praveen Raghavendra and Ahmed Rifaee for your valuable replies.

I just solved the problem, it was causing by the setting has been changed in OPTK without performing CJEN and CJBN. The setting is working after I have done CJEN and CJBN.

Thank you for your contribution.

regards,

FLL