Delivery From Project Complete Technically

fortian
Active Contributor
0 Kudos

Hi,

I would like to make a delivery, using CNS0, but I guess I'm misunderstanding something us when I set the status "complete technically" the materials kind of disappear and I'm not able to make the delivery.

How is suppose to work?

Thanks a lot,

mforman

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Disappearance of components at "TECO" status is standard.

try "CNS0" performs a logistical funtion against the Project which needs the Project status "Not to be TECO"

regards