Resource to change from Single-Mixed to Multi-Mixed

Former Member
0 Kudos

I need to change an existing resource in APO from Single-Mixed to Multi-Mixed.

I have changed the APO resource header in ECC to reflect the same.

However, when I CIF the resource, I still get the resource as Single-Mixed instead of MultiMixed.

The resource tcode res01 in APO shows the current change date, however, it is not yet multi-mixed.

I thought of deleting the resource in APO, however, it is currently used in other PDSs and Orders. and then CIF the resource fresh.

Advice? Is there a way to do the change in APO without deleting and CIFing the new one?

Thanks!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I don't think it is possible.

1.You need to delete the resource is APO

2.Change in R3

3.CIF the resource.

To delete the Resource in APO

1. Need to delete from Model.

2. Delete the Orders whicg are existing.

3.Delete the PPM.

4.Delete the Resource.

Thanks,

nandha