Hello colleagues,
Does anyone know a way to neutralize the affect of Network header basic dates when using Shifting dates from WBS?
Thanks in advance
Best regards,
Nir
Hi
You mean to say without affecting the network dates - you want to shift WBS dates?
Shifting of dates will be at project/ WBS/ sub item level so when you assign network to a WBS element and try to shift the dates, system will try to shift the dates of all the objects in the relation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nir,
In all PS transaction I known, e.g. CJ20N, CJ2B, CN24 or CJ02 , the assigned PM orders are not locked, untill the user triggesr the involved action. And there no locking surely no changes can be done.
The integration with PM in scheduling aspect, it can only happen, if the PM orders are assigned to the network activity. Assign to WBS may be only relevant for the 'costing' report aspect, I am not sure about it.
If a PM order is assigned to an activity, you can either use CN24, switch to the scheduling type to include the PM orders and carry it out. In CJ2B, you have the possibility to show the assigned PM orders of the activity: select the activity and then button 'PM orders'. Then the PM orders should be appear in a screen in the bottom. Select them and the run the scheduling using function of right mouse key.
Kind regards,
Zhenbo
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.