Time taken between GRN and Quality inspection

Former Member
0 Kudos

Hi all,

Once the GRN happens the Qty is moved to the quality inspection and when quality inspection is completed the stock is moved to unrestricted use...so i want the time from the qty moved to Q insp to the time ir reached the unrestricted....

Is there any standard report to find the time taken for quality inspection..???

Regards,

Joseph.

Edited by: joseph5885 on Nov 11, 2010 3:01 PM

Accepted Solutions (1)

Accepted Solutions (1)

former_member207800
Active Contributor
0 Kudos

There is no standard report.

I would suggest to develop a report.

Using QAMB table you can find easily when the material documents are input.

Regards

Luke

Answers (1)

Answers (1)

Former Member
0 Kudos

This is referred as the lead time in QI .This is available in std reports but in SAP std its considered to be the 24 hrs duration.

Refer thread.