1)

Suppose i have 5 seperate BOM's in my Project

I want to pickup only one bom for the required product

how do we do that and what are the setting we need to

2) what are the setting we need to do to link Storagae location to BOM

Regards,

Raj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You need to create different PV's with different lot size. Based on the Lot size you can decide the PV and hence BOM.

Thanks,

nandha

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Raj,

Welcome to SDN !

Check my replies from this links and explore

[Alternative BOM selection - Link 1|;

[Alternative BOM selection - Link 2|;

[Alternative BOM selection - Link 3|;

Regards

Madhu

Former Member
0 Kudos

Dear Raj

As far as your first qusetion goes, I think we can maintain the Quota in APO system. T-code /SAPAPO/SCC_TQ1 - Quota Arrangement By Quota we can decide which BOM (Production version) has to pick for planning in APO.

Thanks