Can any one help me how to create report painter from PS using Z fields which were added in table PROJ by append CI_PROJ?

I need to know how to turn this fields visible to add in creaton of the variable . transaction CJEV.

Thank you

Best Regards

Lina

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I have not worked on it but you can try this out:

TCODE for report writer table is GRCT.

There You need to add your z fields in some pre-defined structure like CCSS and then activate the structure and then activate characteristics.

NOTE: 24 charcter is max. length for the characteristics.

Regards,

Harsh.