Scheduling in Deliveries not copied from the correct schedule line of SO

Former Member
0 Kudos

Hi All

I have availability check activated for sales orders.

In which for a given material it determined 2 schedule line .

Schedule line 1. With 0 quantity -- e.g. delivery date 01.10.2010

Schedule line 2. With 5 quanity -- e.g. delivery date 05.10.2010

The re-scheduling is de-activated for my delivery note (type).

When the delivery note was created, it had planned delivery date = 01.10.2010, and not 05.10.2010.

Why was the date in the delivery copied from the 1st schedule line instead of the 2nd schedule line which was the correct date based on material availability?

What should be done to ensure that the delivery copies the dates from the 2nd schedule line?

Thanks for the answers!

Regards

Rajesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

It is solved. Copy routines did not consider multiple schedule lines.