MRP for project

Former Member
0 Kudos

Dear Experts,

In MD04, they show following data:

Stock : | 40 (Available)

Projct T-10001.1 : | 0 (Available)

OrdRes : 30 (Reqd.qty) | -30

are there anyway to automatic transfer Material from Stock to Projct T-10001.1 when run MRP (MD51)??

Kindly to hearing from you,

NhatLQ

Accepted Solutions (1)

Accepted Solutions (1)

raghavendra_praveen
Active Contributor
0 Kudos

Hi

You cannot transfer the stock from plant stock to project specific through MD51. a separate MM transaction needs to be run for that.

Former Member
0 Kudos

Thanks Praveen Raghavendra,

Anyway, when i run MD51, system generate a Planned Order with quantity is 30 for that project stock,

But with logically, the Planned Order must be 10, (by 40-30)

Answers (0)