Dear Experts,
In MD04, they show following data:
Stock : | 40 (Available)
Projct T-10001.1 : | 0 (Available)
OrdRes : 30 (Reqd.qty) | -30
are there anyway to automatic transfer Material from Stock to Projct T-10001.1 when run MRP (MD51)??
Kindly to hearing from you,
NhatLQ
Hi
You cannot transfer the stock from plant stock to project specific through MD51. a separate MM transaction needs to be run for that.