Hi all,

I m stuck with a critical issue. I m not able to get the cost of maintainance. while creating maintainaince order I m getting ERROR - MISSING FORMULA IN WORK CENTER and a warning message NO PRICE COULD BE DETERMINED FOR INTERNAL ACTIVITY .

I have done everything which I know regarding costing configuration.

I have created activity type ,asigned it to the cost center,assigned parameter to the std value key what else is required.

I m not getting any of the cost in costing tab of maintainance order .

Please help me out.

Thanks& Regards

Pooja

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

1. In Work Center under costing tab , maintain cost center

In work center which you are using in Maintenanace Order operation , please mention the activity type in Act Type Int Proc field and formula as SAP008 in costing tab of work center ..

2. In Schdueling Tab of IR02 mention SAP004 in Other formula Field.

3. In Capacities tab of Work center maintain SAP008 as other formula

4. In KP26 for the combination of cost center , activity type ,version, period maintain fixed price ..

5. Check whether value categories are assigned to cost elements in Config

6. Check whether costing variants are assigned for Planned nd Actual costs to combination of plant and order type ..

plz check the above and then test up again with a new order

regrds

pushpa

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can check the below for planned costs :

1.check whether activity price is maintained KP26 for the work center which your using in MO .

2.Check whether costing and valulation variants are maintained in configuration

3.Check whether the control key entered in operations allows costing

4.Check whether valuation categories are maintained in configuration ..

check this and revert back.