on 11-09-2010 4:51 AM
Hello Gurus.
We are using MTO scenario planning strategy is 25 now we have 2 finish material as A & B in both mateial 1 Componant ROH1 is common now for A ROH1 require 2 No. & for B ROH require 3 No. Oure requirment is after MRP run in MD50 system generate seperate PR for 2 No & 3 No. we want combine PR for 5 No for ROH1. Is it possible in MTO scenario? If yes how can we do that?
Regards.
Hi
It is impossible, the strategy create different segments for each sales order items and the requirement of components are separated by the segments, they can only be collected in the plant segment. I think the strategy 50 can do tha for make-to-order.
Best Regards.
Leon.