We are working on aggregated planning scenario with CTM.
Family A is header product with two members B and C. Demand for B and C are at DC1. These demand is getting fulfilled by manufacturing plant 1. Aggregation at header level is working fine at header plant level (PO is generated), but it is disaggregating PO equally at member plant though selection is in proportion of demand.
Hello Manoj,
Please use Quota arrangements. See the details on the SAP library link below:
http://help.sap.com/saphelp_scm70/helpdata/en/31/74c95595548e428bbbe3e64cf9ffb9/frameset.htm
It should works for your scenario.
Regards,
Michel Bohn