on 11-06-2010 2:30 PM
Hi Experts,
i am facing one problem in sales order .
I have one sales oredr in which there is 10 lines items , in which for first two 10 and 20 line item , i have done scheduling agreement change CN to CP on 01.11.2010 data ,
and for line item 30 , i have done change scheduling agreement CN to CP on 05.11.2010 .
Now i am Devloping one Zreport , in which my client requirment is that change data shoild be apper in this Scheduling field .
in FS , i have mention like this,
Pass salese order and line item into and VBEP u2013 POSNR and get the VBEP - EDATU. by this way way i am not getting teh proper date .
but i am not getting teh proper data , can anyone please explain .
regards,
Manoranjan
HI
You have to use the CDHDR and CDPOS tables in order to get the changed date.
From VBAK or VBAP you may get the object id and pass this into the CDPOS table
CDHDR-UDATE
OBJECTCLASS = CDHDR-OBJECTCLAS
OBJECTID = CDHDR-OBJECTID
regards'
Prashanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.