Hi,
I'm new to SAP and learning SAP SCM. I would like someone to brief me on what the following lines imply, especially 'without MRP, with BOM explosion'.
"dependent requirements must be determined for materials that are planned in SAP ECC. So, you assign the MRP type X0 with MRP procedure X (without MRP, with BOM explosion) to the materials planned in SAP SCM."
Thanks,
Krish
Hi,
If you assign MRP Type X0 for an material means that, this wil be a APO Planned material and can't be planned in ECC.
But forthe components of this materials Dep Reqmts will be created by exploding the BOM of the Header material( for which MRP Type X0) is assigned.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Without MRP , with BOM explosion - means the dependent requiremens are created for this materials from APO.
The MRP will not run in APO. Only the dependent requirements will be created from APO. The MRP for this materials will be executed the ECC or R/3 system to create planned order anb purchase requisitions.
Thanks and regards
Murugesan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.