Capacity Planning in PS - CM32

Former Member
0 Kudos

Hi Expert,

I have a problem when make capacity levelling as below

Can I schedule one network activity (in PS) between 2 work center? because I have just assigned one work center into one activity, so when I use Tcode CM32 to levelling I can't see other work center that I want to schedule. in the other case, I can use CM21 to see many work center but I can't schedule one activity between many work center although I created work center hierarchy already.

So HOW I solve this.

Thanks, Regards

Hoai Vu

Edited by: Hoai Vu on Nov 6, 2010 6:38 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can create two different activity elements and assign respective work centers in elements. Scheduling though would be done based on the work center assigned to the main activity.

rgds

Former Member
0 Kudos

Thanks for suggest, it has solved follow your way.

Regards