on 11-04-2010 8:07 AM
Hi gurus,
SCM 5.0
I am running SNP heuristics for a product and expecting planned orders for it. It has corresponding production data structure and multimixed resource. The resource has an assignd factory calendar and SNP bucket capacity. The bucket capactiy availablity dates of the resouce is consistent with the factory calendar workdays/holidays. Using simple lot for lot strategy, I am expecting heuristics to schedule the planned orders on the dates of the demand in compliance with teh SNP bucket capacity availability of the resource. APO does not schedule on holidays consistent with bucket capactiy. This is true until...
We have a public holiday in factory calendar that needs to become a workday. To remedy this, we put a special rule for the factory calendar and explicitly made that holiday into a workday. The changes were synchronized with APO, and this is also reflected in the bucket capacity of the resourc: former holiday now has bucket capacity after the calendar change. However, when running heuristics, it still does not create SNP planned order on that former holiday that has been changed into workday. Even if it is a public holiday, there is already a special rule for the factory calendar and the resource bucket capacity reflects this correctly. But SNP heuristics seems not to follow this change.
Any ideas on this? looks like a bug.
Hi Edgar,
Yes, when your resource reflects the addional capacity of the holiday turned working day, then it is expected to be considered for the SNP planned order.
Instead of SNP heuristics, you may try to check interactively in SNP planning book, if manual order creation in the bucket works out.
Since this is a mutlimix resource , it can also be checked if in PPDS planned order can be created on the day.
The above checking may not solve your problem , but will get to know if at least manully the bucket is being considered or not.
regards
Datta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We don't have a production calendar maintained. It is only the shipping/receiving calendar that we use. They are both based on the same factory calendar and timestreams were regenerated after the calendar change. Timestreams correctly reflected the holiday to workday change. Concerning our issue, I know that the resource factory calendar should always be prioritized by heuristics over production calendar in location master data. We also have this setting turned on in the global SNP settings in the configuration -> "Consider resource calendar" for SNP heuristics.