cancel
Showing results for 
Search instead for 
Did you mean: 

SNP Planned order not following resource bucket capacity/factory calendar

Former Member
0 Kudos

Hi gurus,

SCM 5.0

I am running SNP heuristics for a product and expecting planned orders for it. It has corresponding production data structure and multimixed resource. The resource has an assignd factory calendar and SNP bucket capacity. The bucket capactiy availablity dates of the resouce is consistent with the factory calendar workdays/holidays. Using simple lot for lot strategy, I am expecting heuristics to schedule the planned orders on the dates of the demand in compliance with teh SNP bucket capacity availability of the resource. APO does not schedule on holidays consistent with bucket capactiy. This is true until...

We have a public holiday in factory calendar that needs to become a workday. To remedy this, we put a special rule for the factory calendar and explicitly made that holiday into a workday. The changes were synchronized with APO, and this is also reflected in the bucket capacity of the resourc: former holiday now has bucket capacity after the calendar change. However, when running heuristics, it still does not create SNP planned order on that former holiday that has been changed into workday. Even if it is a public holiday, there is already a special rule for the factory calendar and the resource bucket capacity reflects this correctly. But SNP heuristics seems not to follow this change.

Any ideas on this? looks like a bug.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Edgar,

Yes, when your resource reflects the addional capacity of the holiday turned working day, then it is expected to be considered for the SNP planned order.

Instead of SNP heuristics, you may try to check interactively in SNP planning book, if manual order creation in the bucket works out.

Since this is a mutlimix resource , it can also be checked if in PPDS planned order can be created on the day.

The above checking may not solve your problem , but will get to know if at least manully the bucket is being considered or not.

regards

Datta

Former Member
0 Kudos

I have tried both and it really does not simply want to create on that date.

Former Member
0 Kudos

Edgar - check if there is a production calendar on the location. Check if it uses the same factory calendar, you may need to regenerate the time series for that calendar and/or adjust the factory calendar.

Regards

Andy

Former Member
0 Kudos

We don't have a production calendar maintained. It is only the shipping/receiving calendar that we use. They are both based on the same factory calendar and timestreams were regenerated after the calendar change. Timestreams correctly reflected the holiday to workday change. Concerning our issue, I know that the resource factory calendar should always be prioritized by heuristics over production calendar in location master data. We also have this setting turned on in the global SNP settings in the configuration -> "Consider resource calendar" for SNP heuristics.

Former Member
0 Kudos

We applied the following notes:

1502915

1381272

1381118

169885

1489437

1435447

1417761

1431419

1448408

and ran the following programs from the OSS notes:

ZZTSTRDELE

ZTTSTRSETTZONE

This fixed the issue.

Answers (0)