Hi Experts,

I have a very basic question.

Can I ever run heuristics without running LLC before heuristics? I know system will not restrict me, but will the planning results be correct?

Regards

Manotosh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

I will suggest to execute the LLC determination in case of you have modeled BOM or executing multilevel heuristic as this information is required to determine the correct planning sequence for the location products, to ensure the demands get fulfilled correctly.

Please find the detail information below for you.

http://help.sap.com/saphelp_scm41/helpdata/en/1c/4d7a375f0dbc7fe10000009b38f8cf/frameset.htm

Thanks

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

The LLC specifies the bill of material (BOM) level and supply chain location at which a location product is situated. The heuristic needs this information to determine the correct planning sequence for the location products, thus ensuring that demands are fulfilled correctly.

Always execute this function before an SNP heuristic run if changes have been made to PPM or T- Lane that are relevant to low-level code determination and thus for the SNP heuristic planning sequence.

Thanks,

nandha

Former Member
0 Kudos

Thank you to all who replied.

yes I am using BOM and was concerned because of that.

Regards

Manotosh