on 11-04-2010 4:51 AM
hI.
We are receving stock at 3rd level of WBS and creating reservation on 4th level of WBS throgh produciton order. My client wants to issue the project stock available at 3rd level of WBS dirrectly to reservation generated at 4th level WBS without any stock transfer. Pl suggest how can i do this.
Regards,
Kalpesh Agrawal
Hi
If requirement generation is at different WBS element then how can you issue the stock from other WBS element in a single transaction? This is not possible. However try with requirement grouping (4th level to 3rd level) concept.