0-100 method Planned POC

Former Member
0 Kudos

In 0-100 measurement method how planned POC is calculated? Does this takes into account of partial confirmation?

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

This basically means that 100% is considered when the component is fully finished.

If you do partial confirmation then it will contribute 0%

Former Member
0 Kudos

Is that mean Planed POC will be 0 till activity in not confirmed? If yes then Planned and Actual POC is same all the time.