Dear All,

The scenario is as follows - Route determination is configured.I am sending 15 Metric Tonnes of Steel from Point-1 to Point-3 via Point-2 by road.The Truck drops 5 Metric Tonnes in Point-2 and 10 Metric Tonnes in Point-3.

How to configure the above.

Someone plzzzzz help

Regards.

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

thanks this thread is closed

Lakshmipathi
Active Contributor
0 Kudos

You have not specified whether you would generate multiple deliveries or with one delivery, this drop shipment will happen.

Assuming that the scenario would be one delivery against multiple shipments, following are my suggestion:-

The Truck drops 5 Metric Tonnes in Point-2

1) Define mode of Transport in 0vtb

2) Define Shipping Types in 0vta

3) Define Transportation Connection Points in 0vtd

4) Defind Routes and Stages in 0vtc

5) Maintain Transportaion Zones in OVR1

6) Define Transportation Groups in OVL7

7) Maintain Route Determination in 0vrf

😎 Tick Relevant for Transport for your Route in 0vtr

9) Define Shiment Types in OVTK

10) Maintain Number Range for this Shipment Type in VN07

11) Define Shipment Cost Types and Item Categories in T_56

12) Define Shipment Cost Relevance in T_57

13) Create Condition Type for your Shipment Cost in T_06

14) Maintain Access Sequence for this condition type in T_07

15) Create and Assign a new Pricing Procedure in T_08

Please note while creating Shipment Type in OVTK, ensure that you maintain as follows:-

a) For the field "ProcessControl", either 2 or 3 is maintained

b) For the field "Leg indicator", Main Leg for first one and Subsequent Leg for the second shipment type

c For the field "Determine legs", it should be blank for the first shipment type

With the above configuration, create a shipment document with first route in VT01N followed by Shipment Cost in VI01 for first stage and secon stage.

thanks

G. Lakshmipathi

Former Member
0 Kudos

Dear All,

Can anyone please tell me the configuration steps in detail for multidrop shipment.

Regards.

Former Member
0 Kudos

Someone plzzzzzzzz. let me the know multidrop shipment process configuration in details

Regards.

Former Member
0 Kudos

hi,

if you have to transfer frieght cost to the customer then at that point of time why you need TM.

simply take the frieght condition type into consideration into sales order it will get copied into delivery document and billing document

this will solve your issue.

Former Member
0 Kudos

hi,

this is to inform you that it is called multi drop shipment or transportation chain in SAP.

if you want to create one single three deliveries in three different locations first you have to configure HUM's.

then,

you have to create one shipment or three shipment documents basing on your requriment and transporataion chain.

then proceed with transportation module configuration.

then settle to the vendor withautomatic service entry sheet.

then go for billing to the customer.

if you want to transfer the frieght cost to the customer not FFA then its a different scenario all together.

regards,

balajia

Former Member
0 Kudos

Dear Balaji,

Could you let me know the configuration steps.

How do I transfer the freight cost to customer.

Thanks.

former_member274400
Active Participant
0 Kudos

Hello Bob,

Are you using transportation management of SAP?

Regards,

Mukul

Former Member
0 Kudos

Hi there,

We are using TM.Could you please let me know the Configuration steps.Why do we require Handling Unit.

Soliciting your kind co-operation in this regard.

Regards.