Hi Experts,
How to CIF Blanket PO's to APO?.How we would run Heuristics.again we are uploading PO's (Normal PO's) to APO. Then how we differentiate between those Normal PO's and Blanket PO's.Here Blanket Po;s are loading monthly and Normal PO's are daily
Regards,
Madhu
Hi Madhur,
When you say 'blanket POs', I understand that you mean 'scheduling agreements'. Scheduling agreements can be ciffed by creating an integration model for SchedAgreement in CFM1.
If you have both scheduling agreements and manual POs, these two would have different number ranges and can be differentiated. Just check and validate.
Regards
Manotosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please also refer to detailed SAP Help on thethe topic of Integrating scheduling agreements.
http://help.sap.com/saphelp_scm70/helpdata/en/9c/787f3c0a771e57e10000000a114084/frameset.htm
regards
Datta
ANswered. Thanks a lot
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Answered. Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.