on 11-03-2010 6:10 AM
Dear All,
We are implementing SAP in one automobile industry, now they r using SPC for Inprocess Analysis. Suppose If production going for 10 hrs every 2 hrsd once they taking 5 samles and recording in sheet. After that the weighted average of sample and range they ploting in SPC. So every month once they checking Graph.
Now Guide Me how to address this scenerio step by step procedure.
In sampling Procedure what Valuation Mode and Control chart type i hve to use ( Here lot of chart type available)?
In MIC what are all Prerequisites required.?
In Inspection for spc mic which spc criterion i have to choose?
Kindly explain me step by step procedure for this scenerio.
What are all configuration required for SPC Chart in background
Regards,
sakthivel
Edited by: ssakthivel on Nov 3, 2010 11:55 AM
Edited by: ssakthivel on Nov 3, 2010 12:02 PM
Hi,
Here is the step by step procedure.
In MIC in the control indicators activate the indicator SPC characteristic.
in the sampling Procedure use valuation mode as SPC inspection as shown below and then assign the control chart type. What control chart type to be used it depends on the business or client requirement.
Now SPC criteria also depends on the business requirement. accordingly choose the required one in the inspection plan for MIC.
Normally configuration is not required much here.
Hope this helps
Thanks
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
http://help.sap.com/printdocu/core/Print46c/en/data/pdf/QMQCSPC/QMQCSPC.pdf
check page 9,10,11 & 32-35
may help you..............!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.