Good Morning PS Gurus,
Once again I request to help me..
What triggers the status CNF (Confirmed) in system status in project builder and how can this status be changed / removed?
Many thanks in Advance.
MM
Many thanks...
Issue was resolved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Only activities can have "confirm' status in projects. Once the activities are confirmed its assciated network gets this status accordingly. The status is used to confirm actual work done on the activity as aganist planned.
To cancel the confirmation, usetransaction-CN29.