CNF (Confirmed) in system status in CJ20N

Former Member
0 Kudos

Good Morning PS Gurus,

Once again I request to help me..

What triggers the status CNF (Confirmed) in system status in project builder and how can this status be changed / removed?

Many thanks in Advance.

MM

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Many thanks...

Issue was resolved

Former Member
0 Kudos

Hi

Only activities can have "confirm' status in projects. Once the activities are confirmed its assciated network gets this status accordingly. The status is used to confirm actual work done on the activity as aganist planned.

To cancel the confirmation, usetransaction-CN29.

Regards

virendra_pal
Active Contributor
0 Kudos

Note - when you do confirmation the final confirmation indicator must be selected for CNF

former_member203108
Active Contributor
0 Kudos

Only activities can have "confirm' status in projects

Hemant, Even WBS elements can have CNF status in projects apart from activities. Enter the actual dates in WBSE, CNF status will be updated for the WBSE.