Hi Experts,

We have nearly 250 plus projects which are using planned cost for the business transactions like commitments and Actuals.

Now we want to use budget functionality to these projects. So I need to assign the budget profile (BUDP) for all these projects. So please guide me is their any special programs or Reports which Assigns budget profile (BUDP) to all these projects. Once I finish this I supposed to copy the planned cost to budget by using the IMCCP3.

Thanks in Advance.

John.

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Go to CNMASS, enter * in project definition field. then select budget profile field in Field selection, enter the budget profile in new value field, then execute it. This will update the budget profile for all the projects in one go.

Former Member
0 Kudos

Thanks Ahmed . Iam closing this.