on 11-02-2010 6:46 AM
dear experts,
in my project, planed cost of production activity cost from production order is flowing to project as project planned cost ,
but i want to restrict this flow of activity cost of production to project as project palnned cost
we want to enter project cost manually
how can i stop flowing of planed cost of activity of production order to project
You have to remove the append indicator for the order catergory 20 (networks) also to stop networks to append planned cost.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Goto OPSV and remove the append indicator from the order catergory 10.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.