dear experts,

in my project, planed cost of production activity cost from production order is flowing to project as project planned cost ,

but i want to restrict this flow of activity cost of production to project as project palnned cost

we want to enter project cost manually

how can i stop flowing of planed cost of activity of production order to project

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You have to remove the append indicator for the order catergory 20 (networks) also to stop networks to append planned cost.

virendra_pal
Active Contributor
0 Kudos

Why remove category 20?

Hemant is correct - Also run CJEN for the project to update the reporting database

Former Member
0 Kudos

Sukender has mentioned that he want to maintain project cost manually, I am assuming that he meant to carry out WBS costing so I asked to supress order category 20 also to avoid addition of cost.

If manual costing means network costing then you are right it is not required.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Goto OPSV and remove the append indicator from the order catergory 10.

Regards

Former Member
0 Kudos

This message was moderated.

former_member203108
Active Contributor
0 Kudos

Actual cost should flow to project, try settling production order to project and then see the report.