Business system name not changing after transport

balaji_pichaimuthu
Active Participant
0 Kudos

Hi,

When we moving the ID object from dev to test , The business system name is not changing. In SLD we maintaing the target system in transport tab for each business but still its not getting changing.

Please let me help

Regards,

Balaji

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

For the Business system in QA did you set the corresponding integration server as QA XI system?

lets say,

the Business system of Dev is ABC_DV and the corresponding integration server is DXI (dev xi system). Now the business system of QA is ABC_QA and the corresponding integration server has to set as QXI (QA xi system) in SLD. Then you can manitain the transport targets in SLD. select the BS, ABC_DV in SLD and assign the transport target for QA of this particular BS as ABC_QA.

also are u using CTS for transports? if so have a look into section 4.3 of below document

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/10456aac-44f7-2a10-1fbe-8b7bcd7bc...

regards,

francis

rajasekhar_reddy14
Active Contributor
0 Kudos

The transport targets what you have maintained in SLD not correct, check once again.

Former Member
0 Kudos

Make sure the corresponding Business System in QA has been already imported from QA SLD and is active in ID.