on 10-30-2010 3:33 AM
Dear Team,
If i am running TLB with Straight Loading Method then i can give priority to Proucts through Loading Group. Now instead of giving priority to product, i want to give priority to Order Size. Lets say i have product A and B. Deployed Qty for Product A is 10 and for B is 20. My TLB profile is of 20. Now if i am running TLB then system is creating one TLB order of 20 (Product B only). What i want is that in TLB priority be given on Order Qty. If i am able to give this priority then my TLB order will be created with 10 qty of Product A and 10 Qty of product B.
Is this possible in Standard System or through some Badi. We are on SCM 7.0.
Regards
Sunil
Hi Sunil,
I believe the priority by Order Size works only in Capacity Leveling, I never heard for TLB.
For capacity leveling there are also the links below:
http://help.sap.com/saphelp_scm70/helpdata/en/cd/208b411fb4b05fe10000000a1550b0/frameset.htm
http://help.sap.com/saphelp_scm70/helpdata/en/e3/e9cc13badd4344a3e0aefb6b9ac265/frameset.htm
Not sure if it helps, but I hope so.
Regards,
Michel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
6 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.