on 10-29-2010 10:42 AM
I have a sales order and a material. The system is not confirming me the material in the same date of the creation (delivery date) but after two working days. Why? The availability check is KP.
Thank you.
Hi,
Chek in shipping point and maintian determine lead time and det pick pack time as blank and check
hope this will solve u r problem
Regards,
Caprin........
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
please check delivery scheduling and transportation scheduling.
and also
check lead time in days in sales document type
and also'
is there any RLT in MMR.
regards,
balajia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check your sales order type configuration in VOV8.
There may be some value in the field Lead Time In Days
If any value is there in this field then Lead Time In Days postpones the requested delivery date by the number of
days you enter in this field.
ELSE check your factory calender
regards
Prashanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
maybe is from the shipping point: 1 day for loading and another day for pick/pack?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.