Hi,

I have few schedule lines.....The one's having zero quantity are not getting CIFFE'd

Can this be the reason for not getting CIFF'ed?

Thanks,

SS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

are you sure they are not ciffed? Check in /SAPAPO/RRP3 activating the flag of "see orders with 0 quantity" to make sure they are not being ciffed.

Kind regards.

Marcos

Former Member
0 Kudos

Hi,

Apologise for the delay in response.............

I had Schedule lines in APO earlier......the user made ttheir quantities 0 and the issue is thst the 0 quantity is not reflecting in R/3 and the SL are not at all appearing in APO.

The R/3 SL are showing with the previous quantity and they all have FIXED INDICATORS set.....Can anyone kindly guide me to fix it

I want the zero quantity to reflect in R/3 SL

Thanks,

SS

Former Member
0 Kudos

Hi SS,

Did you try to run /SAPAPO/CIF_DELTAREPORT3 report to check if inconsistnecs are shown and if necessary corrected ?

regards

Datta

Former Member
0 Kudos

Hi All,

Thanks so much for the prompt responses.............My issue is closed

So I am closing this

Thanks,

SS