on 10-28-2010 1:53 AM
Dear ,
The system considers time relationships between activities from different orders
How i can Create this time Relationships ?
Regards
Rami
Hi,
You can create time relationship between activities of different orders if there is pegging relationship between these orders.
Try using resource buffer from resource master. Also during scheduling scheduling strategy you have to consider pegging and rtime buffers. It will be considered only during scheduling and not during planning.
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I try with Time Buffer , and not working , if you want to protect an activity or the primary resource, on which the activity is processed, from unforeseen delays in material staging, you can schedule using a resource-specific time buffer
Please I need to Create Cross-order relationships ? to consider dependent operation during scheduling
Regards
Rami
Hi,
What I understand from cross order relatioship is
Product A is finshed product manufactured from input product B.
Now you want to have time relationship between planned order of A and Planned order of B. May be you will like to have product B X hours earlier than the start date of product A.
If above is requirement there are two options-:
1.Bom of produt A will have product B as input component. In component details mention operation lead time offset= -X hours if you want component early and +X if you want compont after X hours from start date of order A. This gets transfered in offset consumption feild in PPM/PDS.
While planning dependent requirements are shifted by duration mentioned
But most of times this time is considered while scheduling.
2. You can use resource buffer by mentioning X hours as resource buffer in resource master of resource on which product A is processed. This is not considered while planning but considered during scheduling. Resource before can be used for both within order relationship or accross two bom levels.
Hi Rami,
Cross order/PPM/PDS relationship is not supported by APO.
Plz refer the Note of do's and donts' of cifing PPM/PDS to APO system.
Though there is a provision provided in master recipe (ECC system) in the activity relationship to maintain relationships between operations of diffrent MR's, the same cannot be cifed to APO system atall.
Regards
Sravan maturu
cross order activity relationships cannot be created in by a standard UI in APO PP/DS except for subcontracting orders.
You have to create the relationships by a custom development.
read note 601990 for further information.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Adding a question to your original question...
How can one model a limitation in the time between two different orders? Is it possible to avoid shelf life??
regards,
Pablo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The only way to maintain gap between orders is with setup times.
Shelf lime planning is driven by batch management. If u donot want to use shelflife management then
a. do not activate batch management in ECC system or
b. maintain batch management in ECC and do not cif the charectristics to APO so that shelf life planing will not happen.
Regards
Sravan maturu
Dear Sravan,
Here is the case :
Product A Finished Product Location 1000
Product B Assemply (Input of Product A) location 1100 with Valid PPM
i just need to Reschedule product B as dependent operation based on Reschedule of Product A .
The system considers time relationships between activities from different orders.
Please also tell what's the Note Number
Please I need Your advise
Regards
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.