While doing Scheduling through SAP using internal activity dates get change on every scheduling . Requirement is of Plan vs actual schedule.
Is there any method apart entering plan dates in user field.
Thanks first option will work but option second i.e will be valid for WBS but i have many internal activities for single WBS and comparision is required for various activities.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ahmed,
Is there any way to copy basic/scheduled dates to forecast dates in network apart from doing it through individual networks.
Say i have a networks/subnetwork hierachy basic dates should be copied to forecast dates for all the networks within the hierachy without going into individual networks and changing it through edit > functions > copy dates.
thanks
There are two options:-
1. Make use of project version, to compare the dates of past and present.
2. copy the basic dates to forecast, and compate the present basic date with forecast. do not schedule forecast dates, so that it remains unchanged.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.