on 10-27-2010 6:21 AM
Hi,
We've removed the availability check from 02 to KP in material master for few materials.
But even then while creating the sale order,shhedule line is activate for those materials.
Pls help to resolve the issue.
Harsh
Hi
Even if you have maintained the KP in Material Master the system will confirm the material.
If you want to deactivate the availability check check then goto VOV6 and for your schedule line untick the check box Availability check
regards
Prashanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This is to inform you that even when you removed ACheck from 02 and you kept KP in MMR for few materials even then schedule line is active for those materials.
For that please check define procedures for each schedule line category and requriment class in SPRO.
If you are not satisfied with schedule line level.
Regars,
Balajia.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.