Dear Expert,
I have Dependent Requirement (assembly) Produce in another location , During Rescheduling by Transaction /SAPAPO/CDPS0 For The finished product level i found no rescheduling done for assembly depending on the change of finished product
Appreciate your help
Please Advise
Regards
Rami
Post rescheduling at the finished product try running top down heuristic SAP_PP_010. Include both planning and production location and currosponding resources in propogation range.
Regards,
Santosh