*Hello*

*I dont want to put the cost center in work center as we are not capturing the labour cost. so creating only dumy work center for each plant but the cost center is mandatory in work center*

*I also try to make it non-mandatory through field selection path as shown below but i am not able to that*

*work center -- general data --- define field selection*

Thanks

kapil

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

As you dont want to capure the labour cost and not required to maintain the Cost center, you may not require the "Costing" view to be maintained. In this case , you can avoid entering the cost center instead of using field selection groups.

-Thaila Shree

Former Member
0 Kudos

Hello Thaila shree

Thnx for givin your valuable time ,, solution is ok but now every time at i m getting a pop-up(cost center is not assign to the work center ) at the time of creation of notification, equipment, order.

Is there is any alternate to solution or pl suggest how could remove that pop-up