transfer materials to project from salse order

Former Member
0 Kudos

hi experts,

i wanna know if materials which in sale order can be transfer to project automatically when we use project for assemble-to-order.please help!

best regards

zlf

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

This message was moderated.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ,

CN08 helps do the classi assembly...mat-stdwbs assignment for instance

VA01 create SO and save to have Ps projs created.

remember at a given time only one proj creation is supported.

Regards,

Jemin

Former Member
0 Kudos

thanks all,i think it is not possible to chansfer materials in so to activity auto.

best regards

zlf