on 10-22-2010 1:49 AM
Hi,
I have searched MM, PS & FI forums for an answer to this but found nothing.
In Purchase Requisition, cost can be allocated to a project/WBS element (account assignment). When PR goes for approval it will always go to the person presponsible for the project and not the individual responsible for the WBS element.
Determination comes from table PROJ-VERNR.
How can I make the user responsible for the WBS element become the approver of the PR if they are responsible for the WBS element only and not the project itself.
Config done in CJ20N, OPS6.
Is there a standard way to configure this or perhaps user exit?
Thank you,
Kind Regards,
Will Conlon
I think you are talking about PR release strategy and you want the person responsible in WBSE should release the PR not the person responsible in Project Definition, In that case, I would suggest you to talk to your MM consultant and see whether release strategy can include this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bill,
I agree with, Ahmed's suggestion.
Your MM consultant must have configured the user's ID (in your case, it seems, this person is responsible for project) for PR release (Release strategy).
Determination comes from table PROJ-VERNR
So system is picking from person responsible field in the project definition. If you have done development, instead of picking person's ID from PROJ-VERNR, pick it from PRPS-VERNR. I hope this shoudl work.
Thanks & Regards,
Amaresh Makal
This is not standard
If you want PR to be approved by the WBS resp pers then you need to trigger a workflow or something when using PR release strategy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.