Hi guru,
I'm implementing grant management. I have implemented budget and availability control.
Now, I creatd a budget for a grant of 1000 euro and I posted a FI document of 1001 euro.
The system doesn't give me an error about grant but gives me the following message
commitment budget exceeded
but this error is an FM error (number BP714).
Why the availability control of grant management doesn't work?
Thanks
Regards
10-20-2010 10:31 AM
10-20-2010 4:08 PM
Hi Raffaele,
It depends of your configuration settings. Did you activate AVC in Grants? with which level?