Assign Appropriation Request to WBS level >1

former_member209919
Active Contributor
0 Kudos

Hi,

I have a question related to IM, We need create an appropriatrion request assigned to several WBS ( level 4) but system only let us to assign to level 1 WBS. ( We have seen SAP note 390174).

Does any one know if there is any solution to skip this standard validation?

Thanks,

Sara

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member209919
Active Contributor
0 Kudos

Hi,

Thank you very much for your help, But what is the risk to skip this valiation and link AR to several WBS level 3?

We need AR planning is transfered to several WBS level 3.

Thanks a lot,

Sara

Former Member
0 Kudos

No its not possible.

You can assign only Top level WBS element to an appropriation request. Since it has the hierarchal budgetting and other functionalities.

Praveen

surya_pampana2
Explorer
0 Kudos

I dont think so its possible.

Lets check for the experts comments

Regards

Surya