on 10-18-2010 3:17 PM
Hello Gurus.
Is there a way I can split purchases between two vendors? I have a material that is supplied by two vendors and I want to set it up in SAP so MRP splits the proposals between two vendors; 50% of the weekly requirement to each of these vendors.
How can I set this up?
Quota arrangement concept you can go ahead.
An algorithm with which the system determines the sources of supply for a purchase requisition.
The quota arrangement defines percentages according to which the system assigns purchase contracts as the source of supply.
By setting quotas, you can automatically distribute the purchase requisitions for the duration of a validity time period to different sources.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.