on 10-18-2010 2:34 PM
Hi All,
PDS transfered from ECC to APO in APO does not contain activities.
During transfer message "planner PPU does not exist" pops up.
Can you advise please whats missing.
Thanks,
Regards, Andrey
Hello,
Can you please check where you have maintained 'Planner' on R/3 side ,may in routing and please check if the same
planner needs to be created in APO also.
Rgs- Vikas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Vikas,
Thanks for help.
I checked what you said:
1) there was no planner group assigned in routing in ECC, i assigned it.
2) planner group existed in ECC and in APO.
Still problem exists, and message PPU planner group does not exist pops up. PP/DS does not contain activities.
I don't understand why "PPU" planner group system is refering to since in routing i've selected another planner group.
What else can it be?
Regards, Andrey
Hi,
Have you checked for all the capacity categories the Planner group defined in the R3 resource.
I have simulated this scenario by defining a Capcity planner which is not defined in APO and then started Ciffing the resource.
I am getting the error message " Planner group A does not exist ".
Thanks,
nandha
Hi Nandha,
Yes i've checked all capacity categories.
The issue disappeared after activation queue in APO with error message PPU planner does not exist.
This might be due to different reasons, i don't completely understand since before this issue i didn't have to do additional activations.
One of possible reasons could be slow system performance.
However, issue is solved. Thank you for help!
Regards,
Andrey
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.