Could anyone please tell me how the system proposes a delivery date in SD.....when there is shortage of raw materials used to make the requested finished good. How SD to know when the finished good will be available (ie raw material gets available) and if so, is there any settings we do so that the system automatically calculates the total days and propose a date. The link PP to SD.

Thanking you

nimeboy

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

The goal of shipment and transportation scheduling is to confirm a delivery date for a material requested by a customer. For backwards scheduling, the customeru2019s requested delivery date is used to calculate the material availability date and the transportation lead time. The delivery must be created on the earliest of the two dates (selection date for outbound delivery).

u2022 If both dates are after the order date and the material is available on the material availability date, the customeru2019s requested delivery date can be confirmed. A schedule line is created for the sales document item. The date of the schedule line displays the confirmed delivery date that is the same as the customeru2019s requested delivery date.

u2022 If one of the two dates is before the order date, confirmation of the requested delivery date cannot take place. Therefore, the system attempts to determine the next possible date (forward scheduling).

If the result of backward scheduling means that the delivery date required by the customer cannot be confirmed, the system executes forward scheduling.

­Forward scheduling takes into consideration the time parallels of the work flows for transportation planning and picking/packing of materials. The longer of the two periods is relevant for scheduling. The selection date of the outbound delivery is the earlier of the material availability or the transportation planning date.

The earliest date at which the material is available in the warehouse is the new material availability date. This is the outgoing point for new delivery scheduling.

Two schedule lines are generated for the sales line item:

u2022 ­The date of the first schedule line corresponds to the customeru2019s required delivery date and has no confirmed quantity.