Hi all,

We are on SRM 5.0 Extendec CLassic with ECC 6.0

I have a couple of questions wrt budget check and commitment creation in SRM.

1.When a PRis transferred from ECC to SRM,is the budget check possible?If yes,what are the settings in ECC/SRM?

2. After a PR is transferred to SRM,SC gets created.When creating a SC,is the budget check done?If so,if the funds are available,is acommitment posted to ECC?

3.IF the Budget check error was not encountered at the time of SC creation,while creating a PO,why does the system gives error that "Funds not available".Is this correct?

We have somePR's(inventory) which get transferred to SRM,but after the SC is created and aPO is issued for that SC,systemchecks the budget and throws an error that funds not available.

What we want is that at the time ofPR creation itself,system should check the funds and disallow PRcreation if funda are not available.

Can anyone tell me whether we need to implement the controlin ECC at the of PR creation or is this issue because of no commitment happening at SC level?

Please clarify.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Closing but not answered.

Former Member
0 Kudos

Hi Muthu/Virendra and other xperts,

Any suggestions?