Dear all,
When I am completing the urgnt correction(SDHF), the status of change request (SDCR) is not getting changed to 'Confirmed'.
Is it a standard behaviour ?
How to configure for automatic status change of Change Request to 'Confirmed' when urgnt correction is completed.
Regards
PK
Hi,
Yes. It's a standard behavior.
If you want to do so, add a processing parameter to the action CLOSE.
What to be set is like that of PRODUCTIVE action of SDHF_ACTIONS profile.
ELEMENT: PREDOC_STATUS
Data type: J_ESTAT
Initial value: E0006 <- status "Confirmed" of SDCR
Regards,
Kazuhisa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Here is another way to change the status of precede document.
SPRO: Change Request Management -> Extended Configuration -> Change Transaction -> Change Transaction Types
Define Status Attributes
SDHF / SDHFHEAD / E0008 / / Completed / 6 / SDCR / SDCRHEAD / E0006
This entry means that if the status of SDHF comes to E0008 then the status of SDCR turns into E0006 automatically.
Regards,
Kobayashi
User | Count |
---|---|
83 | |
24 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.