Hi PP Experts,
Please someone help me on my problem regarding changing UoM on routing operation. I have to change or convert the labor time and machine time from CTS (cents of second) to S(second). How can i change that and i have to consider the impact on report such as routing check, standard time checking report and finacial cost.
Thanks for your help.
Edited by: yatch0325 on Oct 13, 2010 7:58 AM
Hi,
1. In the routing change the UOM for standard value to S and eneter the calculated machine time in S.
2.Change the Base qty and the operation unit.
3.Activity type and the cost needs to be checked.
Thanks,
nandha
Edited by: S.Nandakumar on Oct 13, 2010 8:25 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.