Change UoM of on routing operations.

Former Member
0 Kudos

Hi PP Experts,

Please someone help me on my problem regarding changing UoM on routing operation. I have to change or convert the labor time and machine time from CTS (cents of second) to S(second). How can i change that and i have to consider the impact on report such as routing check, standard time checking report and finacial cost.

Thanks for your help.

Edited by: yatch0325 on Oct 13, 2010 7:58 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

1. In the routing change the UOM for standard value to S and eneter the calculated machine time in S.

2.Change the Base qty and the operation unit.

3.Activity type and the cost needs to be checked.

Thanks,

nandha

Edited by: S.Nandakumar on Oct 13, 2010 8:25 AM

Former Member
0 Kudos

Hi Nandha,

This is very useful information but im facing on a large number routes and work centers. Do we have transaction for this? I try to used CA85N it change only the UoM but it fail to change the base value. Or do i have to make a program that will this.