rescheduling the order in planning board

Former Member
0 Kudos

The error is "Activity is outside the planning period" and the detail Log contians 'reschedule activity 180501 0010 0015 S, which is outside the planning period'

(I found that the order valid to order is 04.10.2010 for this perticuler order if this is the reson then how this field is getting updated?)

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check in the initial screen of the access to DS Planning board the planning start and planning end period defined.

You are doing a rescheduling activity which is out side the planning end period.

In the strategy profile you can define that in case of scheduling error termination can happen .

Thanks,

nandha