Hi all.
I am using line item settlement. using investment projects.
Unable to generate the settelemnt rule for the lower level WBS elements. while settling from WBS to AUC
1. Created project (throught AR) with one one level WBS element (top level), planned cost, released budget, posted actual. now while doing settlemnt, i am able to generate settlemnt rule for top level WBS element automatically and settlemnt is done.
2. Created project (throught AR) with TWO level WBS elements (top level and 2nd level), planned cost, released budget, posted actual and while doing settlemnt, i am unable to settle, as system is asking me to maintain settlemnt rule for the 2nd level.
is there a way to generate settlemenmt rule for 2nd level automatically, as i have mainitained settelemnt strategy 40, to take the settlement rule from superior WBS.
i have checked it with CJB2 also, and it giving an error ORB501.
regards
Edited by: Surya Pampana on Oct 12, 2010 12:25 PM
Hi,
In strategy use Account Assignment Category as 5.
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is a BADI for settlement rule generation - try using that
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is your 2nd level WBSE an Account assignment? If yes, doesnt it created an AUC for that line item?
The 2nd level WBSE also gets settled to the respective AUC. Remove the strategy 40 and then try.
Praveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Thanks for the quick response
2nd level WBS is account assigned. in the settelent startegy i have used 4 " copy rule from superior object"
settelment profile also maintained with allocation structure and source structure"
do i have to maintain settelemnt rule manually on 2nd level? OR will be be created auttomatically ???? in std SAP?
Regards
Surya
Please answer this.. does the 2nd level WBSE has an AUC generated for it (check in the system status field, REL AVAC AUC)? If so remove the strategy from the settlement rule parameters and run the settlement using CJ88.
System will automatically creates the settlement rule once the settlement is run.
Praveen
In that case you have to enter the settlement rule manually. Since the acc. assgnmnt option 4 is Copy the rule from superior object. This will copy the settlement rule, if there is any rule exists for the WBSE1, else give the error message.
Alternatively, you can first settle the WBSE1, so that a settlement rule is generated, then run CJB2 for copying the settlement rule as that of WBSE1, in which the WBSE2 is also will be settled to the saeme AUC.
There is also another option to generate the WBSE according to your logic. Implement the BADI WBS_SETTLEMENT_RULE for custom defined rule generation.
Praveen
Edited by: b praveen savan on Oct 12, 2010 6:01 PM
Alternatively, you can first settle the WBSE1, so that a settlement rule is generated, then run CJB2 for copying the settlement rule as that of WBSE1, in which the WBSE2 is also will be settled to the saeme AUC.
I dont think it will work, because you cannot create settlement rule to AUC which is created automatically for another WBSE.
Surya,
You have to create either settlement rule manually for level 2 WBSE or else apply this Note 211324, so that settlement rule automatically created by CJB2, superior WBSE as settlement reciever for level 2 WBSE.
Sorry,
Ahmed is right, we cannot create the settlement rule with receiver as AUC, since the AUC is created through a measure (WBSE).
Surya,
The option lefy is either you have to define it manually, or implement the note mentioned by Ahmed. You have to configure the strategy after the note is implemented.
Prvaeen
Thanks for all the inputs.
Ahmed, i have implement the note 211323 and its relevent notes, still not working.
Ok, if i have to maintain settelemnt rules manully, how to maintain at level 2.
FYI: both level 1 and level 2 are account assigned
Now i have to maintain the settelment rule for 2nd level as : from level 2 to level 1?
pls suggest
Regards
Surya
after applying note, you will see a new account assignment category in Define strategy for settlement rule(IMG). There you have to create a strategy and then assign to project profile.
Ok, if i have to maintain settelemnt rules manully, how to maintain at level 2.
press ctrl+f3 in any change WBSE transaction like CJ20N. there you maintain the settlement rule for level 2 WBSE