on 10-12-2010 11:02 AM
Hi All,
There is a report requirement from my client regarding the changes made into the staffing in cProject.
Please provide me any standard report or table in SAP which can fulfill my requirement.
Following are the fields i m trying to catch from staffing
Project
Project Role
Resourse
changed by
changed on
effort changed
Start date
finish date
Thanks
Abhijeet
Hi Abhijeet,
Project ( dpr_project & cgpl_project)
Project Role (dpr_part & cgpl_task )
Resourse (dpr_part & dpr_bupa_link)
changed by (cgpl_task)
changed on (cgpl_task)
effort changed dpr_part
Start date cgpl_task
finish date cgpl_task
Maybe the codes in the method cl_prp_resource_project~get_tasks will give you more further information.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.