Hai Gurus,
I have one doubt.
1) We are implementing PS for a construction company, earlier my client
does not insisted scheduling, which was done by Primavera, now they
want scheduling to be included in the project under PS.
2) My doubt is the client get all the work done in the site by two ways
a) Material given by the client and work done by the vendor based on the
work order raised ( Manual work order)
b) Some times both material and service done by the vendor itself ( Manual work order)
under this situation can we bring the both case into scheduling , if so how
to define the activity - whether it is internal or external activity for defining
time/cost and to follow the time duration between the actual and planned dates.
waiting for your positive reply.
Regards,
sekar chand
Sekar,
It is possible.
When you create the external activities, generally the control key is taken as PS02 (it depends on configuration) in the customization ensure for the control key - schedule ext. op. option is enabled. (tcode OPSU).
Then the activities defined as the ext. processing can also be scheduled in the PS.
Praveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai Praveen ,
Thanks for your reply.
Actually the service order is raised for all the work to be done by the contract persons,
some times material is given by the client or both material and service is provided by
the contract persons and work order is raised manually.
So can we treat the the service order as external activity and define the date/cost etc
Regards,
sekar chand
You can enter the Service activities in Externally processed activities by enabling the option Service in network, this will create a PR for the services, then convert it to PO and Service Entry sheet.
For the material part you have to create a PR or PO directly if the vendor is supplying the material, it is better to have a diff PO for the materials for better controlling purpose. Else if your client is supplying the materials, create a reservation with moment type 221 and issue the same against the reservation number.
Praveen
Hai Praven ,
Thanks for your detail reply.
My doubt is while creating a activity whether I had to select external activity or
service activity,
Second one when I created external activity i am unable to define the dates for
scheduling.
If i select the activity as service how to define the dates for scheduling
Regards,
sekar chand
My doubt is while creating a activity whether I had to select external activity or
service activity
You have to take it as External activity with Service option enables.
Secondly,
Second one when I created external activity i am unable to define the dates for
scheduling.
After defining the activity, select the activity line and click on Details at the bottom (Magnifier button), you will find a tab Internal in that there is a field Normal Duration at the bottom, enter the duration for the activity.
But please be noted that you have enabled the option Schedule Ext. Op for the control key in the transaction OPSU.
Praveen
In the network header enter the Basic Start or Basic Finish date, this depends on the scheduling type. If it is Forwards, then enter Start date, if it is Back wards, enter Finish date.
You can also use the Dates constraints for the activities, when you open the details screen for the activity, there is a tab Dates, in that you can find Constraints, you can enter the Constraint as Must start on for the activity and enter the date, if you want to give the dates to the activities manually.
Generally the dates for the activities are calculated automatically based on various parameters.
Based on these dates system will schedule the activities. If no date is entered here, system will consider current date as the scheduling date. If you want the to start the scheduling in the past dates, then you have to allow the same in customization. OPU6, there is a field Start in past.
I would recommend you to go through the below link from SDN wiki to understand more about the Project basics on scheduling patterns.
http://wiki.sdn.sap.com/wiki/pages/viewpage.action?pageId=202277792
Praveen
Edited by: b praveen savan on Oct 12, 2010 3:15 PM
You can use internal activities for material & service activities service procurement. But again it depends on the your business scenario.
Regarding scheduling, read SAP help.
http://help.sap.com/saphelp_47x200/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm
Ensure that, in OPSU, you have maintained proper configuration for scheduling.
Thanks & Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.